North Manchester Hospital – Electrical Distribution Upgrade

The Challenge

North Manchester General Hospital required a major upgrade to its electrical distribution systems within critical departments, including A&E, X-Ray, and Infectious Diseases.

The works needed to be completed without shutting down services or decanting clinical areas, presenting significant logistical and technical challenges.

Project Goals

  • Upgrade electrical distribution infrastructure within critical departments

  • Maintain full operational continuity with no shutdowns

  • Improve resilience, safety, and capacity of systems

  • Deliver innovative solutions to minimise disruption

The Result

AC Group delivered a comprehensive electrical upgrade, including new section boards, distribution boards, and sub-main cabling.

Through innovative design solutions such as additional switch cupboards, works were completed without disruption to clinical services. The upgraded systems now provide enhanced resilience and long-term operational reliability.

Project Manager

Andy O’Driscoll & Craig Daly

Brief Description

Electrical distribution upgrade across critical hospital departments

Client

Manchester University Foundation Trust

Project Budget

£835k

Date Started

March 2023