We Fit Any Furniture – Factory Infrastructure Upgrade

The Challenge

A high-output furniture manufacturing facility required significant electrical upgrades following an Electrical Installation Condition Report (EICR). The challenge was to complete extensive remedial works without disrupting ongoing production.

The environment demanded careful planning, out-of-hours working, and a flexible delivery strategy to maintain operational continuity.

Project Goals

  • Address EICR non-compliances and improve overall electrical safety

  • Upgrade distribution and infrastructure to support production demands

  • Maintain continuous factory operations throughout the works

  • Improve accessibility and long-term maintainability of systems

The Result

AC Group successfully delivered a comprehensive electrical upgrade programme with zero disruption to production.

Works were completed through carefully planned sequencing, including early mornings and out-of-hours activity. The upgraded infrastructure now provides improved safety, enhanced load management, and greater resilience to support ongoing manufacturing operations.

Project Manager

Aaron Raynor

Brief Description

Enabling and electrical works supporting mobile radiology scanner

Client

EQUANS

Project Budget

£312k

Date Started

November 2024